Cost Progress

Hover on the green ring to see how much % has progressed financially, based on the total Approved and Paid claims, divided by the Final Forecast Cost. To enable Cost progress, you need to enter 'Claims' in the Cost module.

Time Progress

Hover on the blue ring to see how much time has progressed since the beginning of the project, based on the time elapsed since the start, divided by the total time between start and completion. To enable, Edit the project schedule and select 'start' and 'end' dates.


Earned Value Progress

Earned Value (EV) is the percent of the total budget actually completed at a point in time. EV is calculated by multiplying the budget for an activity or work package by the percentage progress.