Looking to get straight into it and jump start your Project with Mastt? You've come to the right place, as this quick start-up article will help you learn all the basics to get going ASAP and avoid building spreadsheets.

1. Navigate to a Project

Step 1: After logging in, users will land in the 'My Account' area, where we can navigate to a Project by clicking on the Project title or selecting a Project from the drop-down menu.



If you have access to a Portfolio, it will show in the Project drop-down menu prepended with 'Program'.

 


2. View the different Modules


Once you've selected a Project, you will be redirected in the Project's 'Cost' Module. You can navigate to other modules like the Dashboard by accessing the Hamburger Menu




3. Quick 'Cost' Module Overview


In the Project's 'Cost' Module, we have arranged and automated all of the key financial related processes and procedures required for best-practice management of a project without the need to touch a single document or spreadsheet. In the Cost Module, you can observe the following features on that page including:



4. Create and View Budgets


If you have a Project Budget, you can enter it using these steps. Else if you have no Project Budget yet, you can skip straight to Section 5. 


Step 1: From the Three Dots Menu ( ) against the Project’s ‘Cost Plan’ row, select ‘Add Budget’ and enter the Budget title, amount and status.


Step 2: On the ‘Overall’ page, unravel the row by clicking on the unravel wheel to expose the budget you have created. Keep an eye out for unravel wheel throughout Mastt to give you an indication of where data is available for interrogation.


Step 3: View all Project Budgets in the ‘Budgets’ Register.


You can also create Sub-Budgets to build out a detailed, nested Budget structure. Learn more about Sub-Budgets here.


5. Creating Contracts


Step 1: From the 'Overall' Register Click ‘+ Add Contract’ to open the Add Contract form.



Note: You can also add Contracts from the 'Contract' Register.


Step 2: In the Add Contract form, enter the contract title and add milestones/schedule items using ( ) if required. Milestones/contract elements should match the breakdown of the work in the actual contract. Otherwise, the contract can remain without a breakdown.


Step 3: Enter Amounts in the ‘Total Amount’ column; enter ‘Approved’ Status; select a Budget where the Contract should reside, in ‘Under Budget’. 


Note: If you haven't added any Budgets or don't know where to nest the Contract yet, you can come back and edit the Contract later.



Step 4: View the 'Contract' Register to see the created Contract. You can also view the changes on the 'Overall' Register.


Step 5: Only from the 'Contract' Register, you can Edit or Delete the Contract from the Three Dots Menu ( ) next to the Contract’s title.



6. Creating Variations


Step 1: From the 'Overall' Register, Click ‘+ Add Variation’ to open the Add Variation form.



Note: You can also add Variations from the 'Variation' Register.


Step 2: Select a Contract that you are wanting to Vary. The Contract's schedule and information will pre-populate in the Add Variation form.



Step 3: Enter the Variation Title and Variation Status at a minimum.


Note:

  •  ‘PENDING’ and 'FORECAST' status variations will appear on the ‘Overall’ page under the column ‘Forecast & Uncommitted’, 
  •  'APPROVED’ or ‘IN PRINCIPLE’ status will show under the ‘Variations’ column. 


Step 4: Enter a Variation Amount. Where a Variation is linked with a Contract’s milestone directly, it can be entered against that milestone’s row. Otherwise, Variations that are not attributable to a milestone are entered against ‘Other Commitments’. 



Step 5: Click ‘Add Variation’ at the bottom right hand-side of the form to complete the input.


Step 6: View the Variation created in the ‘Variation’ Register.You can also view the changes on the 'Overall' Register where Variations appear under the 'Variation' column.


Step 7: Only from the 'Variation' Register, You can Edit or Delete the Variation from the Three Dots Menu ( ) next to the Variation's title.


Note: Variations that have Claims/Payments against them cannot be deleted or edited to below the Claimed amounts.



7. Creating Claims & Invoices


Step 1: From the 'Overall' Register, Click ‘+ Add Claim’ to open the Add Claim form.



Step 2: Select a Contract. The Contract's schedule and current Claim information will pre-populate in the Add Claim form.


Step 3: Enter a Claim title, such as ‘Progress Claim 1’ and select a Status.


Note: 

  • DRAFT and SUBMITTED status will not be reflected on ‘Overall’.
  • APPROVED and PAID status Claims appear in the ‘Paid To Date’ column on ‘Overall’ page.
  • PAID status Claims will require a Cash Flow Month to be entered, which will appear automatically on the Cash Flow Register.


Step 4: Enter the Total Value Complete or the Net Claim amounts, either method is correct and the other will self-calculate.


Step 5: Once you're happy with the Claim as it appears on screen, click ‘Add Claim’. 


Step 6: View the Claim created in the ‘Claims’ register. You can also view the changes on the 'Overall' Register at Claim related columns on the right hand side of the 'Overall' table.


Step 7: Only from the 'Claims' Register, you can Edit or Delete the Claim from the Three Dots Menu ( ) next to the Claim's title, in addition to produce a PDF Report (Claim Schedule) of the Claim.



8. Forecast Costs


Forecast costs, also known as uncommitted costs, are important to build out an accurate Final Forecast Cost on the 'Overall' Register for our Project. These are costs that are not yet committed, but known to be spent at a future time. It is important to maintain an accurate Final Forecast Cost so that the ultimate cost to complete the Project is well understood. Forecast costs can be added using'+ Add Forecast' tool, however for this example we will use the short hand method via the Three Dots Menu.


Note: If you are looking for Cash Flow, visit here.


Step 1: From the Three Dots Menu ( ) against the item you wish to insert a Forecast within, select ‘Add Forecast’ and enter forecast information. Once you've entered the Forecast title and Amount, click 'Create Forecast'.



 Step 2: View the Forecast in the ‘Forecast’ Register


Step 3: Only from the 'Forecast' Register, you can Edit or Delete the Forecast from the Three Dots Menu ( ) next to the Forecast's title.



9. Cash Flow


Once your Project is showing an accurate Final Forecast Cost, the spend profile of the Final Forecast Cost across months and financial years can created in the 'Cash Flow' Register.


Step 1: From the Cash Flow page, enter Cash Flow manually by clicking on a ‘$’ field in the table under the desired month to open an input field. 


Note:

  • Cash Flow can only be entered against Contracts, Variations and Forecasts. They cannot be input against Budget Rows.
  • PAID status Claims appear in the Cash Flow automatically with a green background.


Step 2: Navigate to future or past financial years from the Year's drop down menu.




10. Detailed Views


For all Budgets, Contracts, Variations, Forecasts and Claims, the user can click on the ‘title’ to access a Detailed View of that item. An example for accessing and navigating in the Contract Detailed View is shown below.


Step 1: From the ‘Contracts’ register or ‘Overall’ page, click on the title of the Contract.


Step 2: Navigate the Detailed View of that specific Contract by using the mini tabs. The mini tabs display only information relevant to the selected Contract, including Comments and Attachments.



11. Commenting and Attachments


For all Budgets, Contracts, Variations, Forecasts and Claims in Mastt, the user can add attachments and make comments for viewing in that item’s Detailed View. An example using the ‘Add Claim’ form is shown below, indicating where to attach document and make comments.



12. Other Important Things!


  • Downloading data to Excel
  • Show and hide columns
  • Generate reports